Hot Rolled Steel Furnace Project
As part of the technical re-equipment of mill 2000, Stellar carried out
the sequential dismantling of two furnaces with walking beams, each
with a capacity of 280 tons/hour, followed by the construction of two
new ones, each with a capacity of 400 t/hour.
The contract was partially concluded on EPC terms: the supply of
furnaces was carried out by the French supplier Fives Stein, while
Stellar carried out the full range of QMS, including the development of
working documentation and the purchase of materials.
Also, as part of the reconstruction, it was planned to stop production
for major repairs, during which Stellar replaced the loading/unloading
rollers, working around the clock and completing the work in 5 days.
Work on the entire facility was carried out in two shifts under operating
production conditions and was completed 40 days ahead of schedule.
Concrete Works: 3 000 m3
Refractory: 3 500 tons
Equipment Works: 5000 tons
Piping Works: 80 000 wdi
E&I Cabling Works: 240 000 m